TRANTERS98 TRANTERS AVE · CAMP HILL · THREE-HOUSE DEVELOPMENT
v5 · 15 Sep 2026
98 Tranters Ave unconditional — settles 16 Nov 2026. Three lots: 94 (Lot 194 · 1,765 m² — Blake & Mel's new home), 96 and 98 built and sold individually. Tap a phase for its tasks · Accountability list below shows every item with its owner and rough date. In Edit mode anyone (yes Tam, you) can add or change items — then hit Send changes to Jarvis.
Settlement
16 Nov 2026
98 Tranters Ave
House 94 start
Apr 2027
earmark — earlier if possible
House 96 start
≈ Aug 2027
~4 months after 94
House 98 start
≈ Oct 2027
~6 months after 94
Done Act now Waiting — dependency Later stage ✎ local edits not yet sent

Accountability — every item, one list

Click a column heading to sort by phase, owner, date or status. Dates are rough targets — say so if any are wrong.
PhaseItemAccountableRough dateStatus

Crew & Contacts

Eric — Chip Off The Old BlockArborist. Tree clearing immediately post-settlement. Ecology + bushfire reports already permit removal.
Andrew Pine — Pine LawLawyer. Drafts connections easement off the new survey plan, ASAP.
Richard — Lateral CertificationBuilding approvals for all three houses (incl. dummy BA sets for 96/98).
Civil engineer (TBC)Civil design, easement sizing, runs the operational-works approval process.
Geotech engineer (TBC)Soil tests + rock-stabilisation check of contoured earth along the easement path.
Surveyor (TBC)Documents easement size on a new survey plan once civil feedback lands.
Ecology + bushfire consultantsReports already in hand (clearing approved). Updated reports needed for the 96/98 upsize stage.
Tranters Ave, Camp Hill. All three design briefs (94/96/98) received by Elevate 14 Sep. Lot/address mapping (Lot 194 → 94 Tranters, 1,765 m²) and Apr+4/+6 month starts per Blake's brief — correct anything in Edit mode. Edits are saved in this browser immediately; hit “Send changes to Jarvis” to make them official for everyone.
Item
Status
Rough date
Accountable
Notes